In Texas Oil Country, Wind Is Straining the Grid
https://www.technologyreview.com/s/602112/in-texas-oil-country-wind-is-straining-the-grid/August 6, 2016
The Lone Star state is by far the largest state for wind power, with nearly 18,000 megawatts of wind generation capacity already built and another 5,500 megawatts—nearly equal to California’s total installed capacity—planned. The biggest driver of that wind boom was an $8 billion transmission system that was built to bring electricity from the desolate western and northern parts of the state to the big cities of the south and east: Dallas, Austin, San Antonio, and Houston.
Completed in 2014, the new wires—known as Competitive Renewable Energy Zones, or CREZ—have the capacity to carry some 18,500 megawatts of wind power across the state. That’s not enough to handle the 21,000 megawatts of capacity Texas expects to reach this year, and it’s creating a situation that’s straining the transmission system and potentially resulting in periods where the turbines go idle.
Now the state’s utilities and transmission companies are faced with spending hundreds of millions more to upgrade the system, demonstrating just how costly and complicated it is to shift from fossil fuels to renewable sources of energy, even where those sources are abundant.
EDF Renewable Energy, which owns five wind farms in northern Texas, and other operators have proposed adding second lines to existing transmission lines from the panhandle, where much of the new wind-farm construction is happening. Doing so, EDF says, will accommodate nearly 4,000 megawatts of new generation expected in the panhandle over the next several years.
“If some of these projects get developed in the panhandle and they haven’t done the upgrades to the grid, for sure those farms will be curtailed,” says Frank Horak, the CEO of Austin-based energy consultancy Astek Energy....