Author Topic: Navy Destroyer Modernization Program Could Cost $17B, Take Up to 2 Years Per Hull  (Read 122 times)

0 Members and 1 Guest are viewing this topic.

Offline rangerrebew

  • TBR Contributor
  • *****
  • Posts: 165,766
Navy Destroyer Modernization Program Could Cost $17B, Take Up to 2 Years Per Hull
By: Sam LaGrone
January 31, 2023 7:35 PM
 

ARLINGTON, Va. – The plan to upgrade the Navy’s fleet of Flight IIA Arleigh Burke guided-missile destroyers with new radars and electronic warfare suites is estimated to cost about $17 billion and take anywhere from a year and a half to two years to upgrade each warship, USNI News has learned.

The service has been working for the last several years to develop a plan to back fit about 20 Flight IIAs with the AN/SLQ-32(V)7 Surface Electronic Warfare Improvement Program Block 3, the AN/SPY-6 air and missile defense radar and the Baseline 10 version of the Aegis Combat System.

The DDG MOD 2.0 effort is starting with the first installation of SEWIP aboard USS Pinckney (DDG-91) during a $121 million modernization period currently underway at General Dynamics NASSCO shipyard in San Diego, Calif.
 
https://news.usni.org/2023/01/31/navy-destroyer-modernization-program-could-cost-17b-take-up-to-2-years-per-hull
The legitimate powers of government extend to such acts only as are injurious to others. But it does me no injury for my neighbor to say there are twenty gods, or no god. It neither picks my pocket nor breaks my leg.
Thomas Jefferson

Offline rangerrebew

  • TBR Contributor
  • *****
  • Posts: 165,766
This could end all wars!  If innovations keeping taking longer and longer, there won't be enough ships to have a battle! :whistle:
The legitimate powers of government extend to such acts only as are injurious to others. But it does me no injury for my neighbor to say there are twenty gods, or no god. It neither picks my pocket nor breaks my leg.
Thomas Jefferson