USS Gerald R. Ford Needs Parts from Carrier Kennedy for Repairs; Navy Says ‘Cannibalization’ Won’t Delay JFK Schedule
By: Mallory Shelbourne
November 15, 2021 6:43 PM
Carriers USS Gerald R. Ford (CVN-78) and John F. Kennedy (CVN-79) at Newport News Shipbuilding on Nov. 12, 2021. USNI News Photo
The Navy is taking parts from an aircraft carrier currently under construction and placing them on USS Gerald R. Ford (CVN-78) so the lead ship is ready to deploy next year, USNI News has learned.
The parts are coming from the future USS John F. Kennedy (CVN-79), the second ship in the Ford class of aircraft carriers that is currently under construction at Huntington Ingalls Industries’ Newport News Shipbuilding in Newport News, Va.
Capt. Clay Doss, the Navy’s acquisition spokesman, told USNI News the parts taken from Kennedy for Ford range from pumps to limit switches.