Watchdog: 75 percent of sub and aircraft carrier maintenance ended late in recent years
Geoff Ziezulewicz
 

While the U.S. Navy has spent nearly $3 billion to improve shipyard maintenance performance in recent years, “the shipyards continue to face persistent and substantial maintenance delays that hinder the readiness of aircraft carriers and submarines,” according to a government watchdog report released this week.

Three-quarters of the 51 aircraft carrier and submarine maintenance periods from fiscal 2015 to 2019 were completed late, resulting in 7,425 days of delays, according to the report by the Government Accountability Office.

The Navy’s four shipyards — in Portsmouth, Virginia; Kittery, Maine; Honolulu, Hawaii; and Bremerton, Washington — provide vital maintenance that includes ship overhauls, nuclear refueling, alterations and refits, among other duties.

https://www.navytimes.com/news/your-navy/2020/08/21/watchdog-75-percent-of-sub-and-aircraft-carrier-maintenance-ended-late-in-recent-years/