GAO: Navy Lost 1,891 Days of Attack Sub Operations Waiting for Repairs; Spent $1.5 Billion Supporting Idle Crews
By: Sam LaGrone
November 19, 2018 2:39 PM

 

Delays in maintenance have resulted in at least 1,891 lost operational days for the U.S. attack submarine fleet and cost the Navy about $1.5 billion to support boats that can’t go to sea, according to a Monday report from the Government Accountability Office.

From 2008 to 2018, most of the planned repairs for the Navy’s fleet of about 50 nuclear attack submarines have started late and run long resulting in a combined 10,363 days of maintenance delays and idle time.

“Our analysis found that the primary driver affecting attack submarines are delays in completing depot maintenance,” read the report. “For example, of the 10,363 total days of lost time since fiscal year 2008, 8,472 (82 percent) were due to depot maintenance delays.”

https://news.usni.org/2018/11/19/gao-navy-lost-10000-days-of-attack-sub-operations-waiting-for-repairs-spent-1-5-billion-supporting-idle-crews