Carrier USS John C. Stennis Overhaul Delayed, Work Will Take More than 5 Years to Complete
SAM LAGRONE
JUNE 18, 2024 2:52 PM - UPDATED: JUNE 20, 2024 10:48 AM
 

NEWPORT NEWS, Va. – The midlife overhaul and refueling for aircraft carrier USS John C. Stennis (CVN-74) will now take about five and a half years to complete – an extension of almost 14 months, according to Navy Fiscal Year 2025 budget documents.

Stennis began the refueling and complex overhaul in 2021 and was due to finish the massive, multi-billion overhaul by August 2025. However, that date was pushed to the right by more than a year to October 2026, according to the Fiscal Year 2025 budget documents released earlier this year.

Speaking to USNI News on Monday, program executive officer carriers Rear. Adm. Casey Moten said the delays are due to the workforce and material shortfalls that stretched out the delivery of USS George Washington (CVN-73), which were made worse by the restrictions due to the COVID-19 pandemic.

https://news.usni.org/2024/06/18/carrier-uss-john-c-stennis-overhaul-delayed-work-will-take-more-than-5-years-to-complete
The unity of government which constitutes you one people is also now dear to you. It is justly so, for it is a main pillar in the edifice of your real independence, the support of your tranquility at home, your peace abroad; of your safety; of your prosperity; of that very liberty which you so highly prize. But as it is easy to foresee that, from different causes and from different quarters, much pains will be taken, many artifices employed to weaken in your minds the conviction of this truth.  George Washington - Farewell Address