Navy Destroyer Modernization Program Could Cost $17B, Take Up to 2 Years Per Hull
By: Sam LaGrone
January 31, 2023 7:35 PM
 

ARLINGTON, Va. – The plan to upgrade the Navy’s fleet of Flight IIA Arleigh Burke guided-missile destroyers with new radars and electronic warfare suites is estimated to cost about $17 billion and take anywhere from a year and a half to two years to upgrade each warship, USNI News has learned.

The service has been working for the last several years to develop a plan to back fit about 20 Flight IIAs with the AN/SLQ-32(V)7 Surface Electronic Warfare Improvement Program Block 3, the AN/SPY-6 air and missile defense radar and the Baseline 10 version of the Aegis Combat System.

The DDG MOD 2.0 effort is starting with the first installation of SEWIP aboard USS Pinckney (DDG-91) during a $121 million modernization period currently underway at General Dynamics NASSCO shipyard in San Diego, Calif.
 
https://news.usni.org/2023/01/31/navy-destroyer-modernization-program-could-cost-17b-take-up-to-2-years-per-hull
abolitionist Frederick Douglass: “Power concedes nothing without a demand. It never did, and it never will.”

Offline rangerrebew

  • TBR Contributor
  • *****
  • Posts: 184,530
This could end all wars!  If innovations keeping taking longer and longer, there won't be enough ships to have a battle! :whistle:
abolitionist Frederick Douglass: “Power concedes nothing without a demand. It never did, and it never will.”