Report to Congress on Columbia-class Submarine Program
« on: February 20, 2025, 10:55:22 am »
Report to Congress on Columbia-class Submarine Program
U.S. Naval Institute Staff
February 20, 2025 8:21 AM

The following is the Feb. 5, 2025, Congressional Research Service report, Navy Columbia (SSBN-826) Class Ballistic Missile Submarine Program: Background and Issues for Congress.

From the report
The Navy’s Columbia (SSBN-826) class ballistic missile submarine (SSBN) program is a program to design and build a class of 12 new SSBNs to replace the Navy’s current force of 14 aging Ohio-class SSBNs. Since 2013, the Navy has consistently identified the Columbia-class program as the Navy’s top priority program. The Navy procured the first Columbia-class boat in FY2021; the boat was funded with three-year incremental funding in FY2021-FY2023. The Navy procured the second Columbia-class boat in FY2024; the boat is being funded with two-year incremental funding (also called split funding) in FY2024-FY2025. The Navy wants to procure the remaining 10 boats in the program—boats 3 through 12—at a rate of one per year in FY2026-FY2035.

The Navy’s FY2025 budget submission estimates the total procurement cost of the first boat at $15,179.1 million (i.e., about $15.2 billion) and the procurement cost of the second Columbia-class boat at $9,283.1 million (i.e., about $9.3 billion). The first boat’s procurement cost is much higher than that of subsequent boats in the class because the first boat includes most of the detail design/nonrecurring engineering (DD/NRE) costs for the class. (It is a long-standing Navy budgetary practice to incorporate the DD/NRE costs for a new class of ship into the total procurement cost of the first ship in the class.) The first boat’s estimated procurement cost includes $6,557.6 million for plans, meaning (essentially) the DD/NRE costs for the class. Excluding costs for plans, the estimated hands-on construction cost of the first ship is $8,621.5 million (i.e., about $8.6 billion).

The Navy’s proposed FY2025 budget requests $3,341.2 million (i.e., about $3.3 billion) in procurement funding to complete the procurement cost of the second Columbia-class boat and $6,215.9 million (i.e., about $6.2 billion) in advance procurement (AP) funding for Columbia-class boats to be procured in FY2026 and subsequent years.

Issues for Congress for the Columbia-class program include the following:

https://news.usni.org/2025/02/20/report-to-congress-on-columbia-class-submarine-program-2
The unity of government which constitutes you one people is also now dear to you. It is justly so, for it is a main pillar in the edifice of your real independence, the support of your tranquility at home, your peace abroad; of your safety; of your prosperity; of that very liberty which you so highly prize. But as it is easy to foresee that, from different causes and from different quarters, much pains will be taken, many artifices employed to weaken in your minds the conviction of this truth.  George Washington - Farewell Address